on 10-08-2014 4:29 AM
Hi gurus,
i want to deactivate budget availability control for some projects. what is the tcode for deactivation.
regards,
siddu.
Hi Siddu,
CJBW is the T-code for deactivating availability control.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siddu,
You can achieve it by using the following methods:
1. Use T Code CJBW to deactivate the budget check.
2. In your budget profile settings for Activation of Budget AVAC check keep it blank..
3. You can also create a separate Budget Profile with no Budget check and assign that to your projects where budget check is not required..
Enjoy!!
Regards
Sammar.
Message was edited by: sammar razdhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.