i want to deactivate budget availability control for projects

Former Member
0 Kudos

Hi gurus,

i want to deactivate budget availability control for some projects. what is the tcode for deactivation.

regards,

siddu.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Siddu,

CJBW is the T-code for deactivating availability control.

thanks

Answers (1)

Answers (1)

sammar81
Employee
Employee
0 Kudos

Hi Siddu,

You can achieve it by using the following methods:

1. Use T Code CJBW to deactivate the budget check.

2. In your budget profile settings for Activation of Budget AVAC check keep it blank..

3. You can also create a separate Budget Profile with no Budget check and assign that to your projects where budget check is not required..

Enjoy!!

Regards

Sammar.