on 10-07-2014 1:36 PM
Hi All
Can we implement below scenario in APO
During the Substitution logic, if the system did not find the enough stock for the actual and substituted material, will it create the planned order for those material and quantity ?.
Ex: Sale order qty : 1000
Main Product stock : 250
ALternative Product : 250
Unconfirmed qty : 500
Can I create planned order for that confirmed qty(note iam usinng prodtct substitution)
If it possible kindly share solution.
Reagrds
Sudhakar
Hi Sudhakar,
You can implement CTP ( Capable to Promise ) to get the planned order created. Did you try this ? You need to enable this in Check Instructions.
Babu Kilari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhakar,
I have not used this functionality. So, you need to test this. But, I expect it not to create any side effects.
In the Check instructions, choose select value 1 for the field StartProduction. This way after fulfilling the ATP in case if there are still some shortages, production can be triggered. Hope this helps.
Babu Kilari