on 10-06-2014 5:39 PM
Hi,
I need to put forecast date to one operation network, but this operation has the particularity that was placed after of plan project, and now I need to transfer basic dates to forecast dates
Thanks in advance
1. Open the network using T code CJ20N - Goto - Project Planning board
2. Select all activities
3. Edit - Reconcile Dates - Transfer Basic dates to Forecast.
Hope you help this.
With regards,
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cesar,
In Project planning board menu ( t code CJ2B), Select Operation Network and go to menu
Edit -> Reconcile Dates -> Transfer basic date to forecast
Forecast dates can be determined via scheduling in the same way as basic dates.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.