How put forecast date to operation network

gocho14
Explorer
0 Kudos

Hi,

I need to put forecast date to one operation network, but this operation has the particularity that was placed after of plan project, and now I need to transfer basic dates to forecast dates

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member210872
Participant
0 Kudos

1. Open the network using T code CJ20N - Goto - Project Planning board

2. Select all activities

3. Edit - Reconcile Dates - Transfer Basic dates to Forecast.

Hope you help this.

With regards,

Dnyanesh

Former Member
0 Kudos

Hi Cesar,

In Project planning board menu ( t code CJ2B), Select Operation Network and go to menu

Edit -> Reconcile Dates -> Transfer basic date to forecast

Forecast dates can be determined via scheduling in the same way as basic dates.


Regards

Tushar

gocho14
Explorer
0 Kudos

Thanks a lot Tushar