on 10-06-2014 10:52 AM
I have the below requirement please advise the best approach?
I have company code and plant "SUP1" in China.
And i have one more company code and plant "REP1" in Korea.
The Customer is in Korea and this customer place a order with company Korea (Korea company code is into Trading business ( buy the stock from China company code and sell it to Korea customers)
and Korea company receive the goods from China plant to Korea plant first then from Korea plant again the goods delivered to Korea customer.
Please note if the goods directly can be moved to customer in Korea from the delivering company code ( China) i could have mapped this through Std Inter company billing process.
But here first goods are coming to Korea plant first then again from Korea plant, goods moving to customer This is the Client requirement exactly don't know the reason.
So in this process how best we can map in SAP ?
thanks,
surya,
1. goods from China to Korea - Intercompany STO process
2. sale from Korea plant to customer - standard sale process
TW
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi TW,
Thank you for your valuable suggestion and time. I was thinking the same direction.However, have some doubts in this is it the below process follows?
1. Korea company creates sales order VA01 after receiving PO request from Korea customer.Here system checks the available stock, let us assume enough stock is not available in Korea plant ( then in Korea plant creates STO PO to China plant ,China plant delivery( VL10D) the goods to Korea plant and do Inter company Invoice (IV) to Korea company.
by considering the above RLT and other required parameters of availability check system confirm the schedule lines let us say after 15days
2. Create delivery to customer VL01N (LF)
3. Creates customer invoice VF01 (F2).
Is that above approach is correct?
thanks,
Hi Surya
For STO you should not wait for the Korean customer's PO. Korean Plant should have the inventory and should trigger STO as soon as the stock goes done to a certain level. This will improve the lead time for Korean customer to get the product on time.
Other things will be same as mentioned above like:
1. STO order from Korea to China
2. Sales from Korea plant
Both steps should be independent.