Original Budget as a Progress Measurement baseline

0 Kudos

Dear Experts - I would like to know if it is possible to set Progress Version with 'Original Budget' as a baseline. This should exclude any Budget Changes - Supplements, Returns, Transfer etc.

I was not able to set the same using standard configurations

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member210872
Participant
0 Kudos

Hi shivpriye,

I didn't get your exact requirement, request you please elaborate.

what I understood from your containt is, you want to crate version of your project with budget as base line so that nobody can able to change it during execution phase.

1. Create Project budget.

2. Create Project version T. Code CN72 with version key

3. Now your base plan is saved in project version.

4. While execution your operative project data will be changed and version data will be as it is.

5. You can see/compare your real time project and baseline data in T. Code CN41N by selecting version data.

Hope this will help you.

With regards,

dnyanesh