on 10-03-2014 5:08 PM
Hi,
I have a project with dates, resorces, progress updated but I need to compare with the original schedule, so I need to see the Baseline
Where with transaction?
Thanks in advance
Hi
You need to explore project planning board and its related profile parameters etc to compare . T-code CJ2B.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cesar,
To see your base line plan you have 2 options
Method (A)
1. Transfer basic dates in to forecast by
Cj20n - Select Project Def - go to project planning board (Shift F8) - Select All project/Actvities/WBS/ (Ctrl+shift+F1) - Go in Edit - Reconcile dates - Transfer basic dates to forecast
Now your base line plan is created (you can see the baseline plan by selecting activity in project builder - Setting - Set of dates - Forecast)
2. Now your base line date = Forecast date and regular project planning date = Basic dates
3. while execution phase of the project your basic dates will get change but forecast date will remain as it is.
4. you can compare your base line (forecast date ) with basic dates by T. Code CN41n/CN47N by change layout and select field project plan date & forecast date.
Method (B)
1. Create Project version at initial stage by CN72.
2. Compare current operative project with version by T code CN41N with selection of version key.
With regards,
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Cesar,
You can use t code CJ2B - Change Project Planning Board
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.