on 10-03-2014 9:35 AM
Hello SAP's,
I have a fairly simple problem many of you might think. I need to assign a P.O. to a network activity in WPS. I would be grateful, if someone could guide me to how this is done.
Best,
Jasper
Hi Jasper,
You cannot assign a PO directly to the network activity. Generally a material PR/service PR is generated from the activity following which the PR is converted into a PO. The purchase order shall be created with the reference of PR created from the project.
Regards
Varun R