Needed some info on an issue we are facing in our project. We have a capacity leveling background job which keeps on failing with the error message- No Valid PPM/PDS found. While checking the variant, we zeroed down on one location product which has Planned Orders on one of its PDSes which is not valid anymore. Rest of the orders in the Liquid horizon are all on valid PDSes.

Question- Why is capacity leveling touching a planned order in the Extended SNP Production horizon (since as per standard SAP,Heuristics and cap leveling should both restrict themselves to Liquid horizon only)?

When we change the start date of capacity leveling horizon in the background job , the job completes successfully. However, shouldnt the cap leveling job restrict itself to level orders only beyond the liquid horizon (irrespective of whatever is start date in the variant)?

Thanks,
Kunal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kunal,

This really a good observation. We also have seen this type of issue in the past, but the order was not in SNP production horizon/extn. prod. horizon. So, after we found the the order (where there was no valid PPM/PDS), we deleted the order to resolve the issue. Basically those orders are hanging orders with no capacity consumption in resourse.

Now, I guess when capacity leveling program starts it select all the orders available in the leveling horizon and do the consistency check. After this task is finished its start to perform the leveling job and this time its exclude the orders which falls in the SNP production horizon (based on the setting in the profile).

So, in your case the job is failed in the first step itself.

Thanks,