Availability for Business Partner

Former Member
0 Kudos

Hi all,

Could someone tell me what drives the availability of a Business Partner if I do not set the Location or the availability directly for the business Partner?

Are there any global customizations where we can set a standard availability? If so could you point me in the direction?

Bets regards,

Morten

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ho Morten,

This is defined in the config IMG > SAP PPM > Project Management > Resource Management > Basic Settings for Roles > Make General Settings for Distribution.

Regards,

Lashan

Former Member
0 Kudos

Hi Lashan,

Thank you for the quick reply!

Regards,

Morten