Hello Forum,

We get the demand from customer in weekly bucket  which currently we are putting in same weekly bucket as sales schedule line qty - which means entire demand is scheduled on first day of the week.


Going forward we want to first disaggregate this demand from customer in weekly demand to daily bucket (evenly across all weekdays) before running MRP. In this way the demand is spread evenly across weekdays to production plant. 


Question : Is it possible to disaggregate the demand from weekly bucket to daily bucket as sales schedule line qty in standard SAP ?


Cheers

Sam

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

You can very well key in manually with different dates at schedule line level.