on 09-30-2014 9:55 AM
Hi all,
I'd like to perform a back up of an SNP Planning Area before doing some activities on it.
What should be the best procedure to do this activity?
Is there any standard transaction by which it's possible to copy massively all the TS Key Figures from the original PA to the back up one?
Many thanks,
SM
Hi MS,
If you want to copy planning area data to an InfoCube for backup use program: /SAPAPO/TS_PAREA_TO_ICUBE
http://help.sap.com/saphelp_scm70/helpdata/en/99/3dc95360267614e10000000a174cb4/content.htm
Check also these two notes:
428147
- Extraction of data from an SNP planning area
632357
- Backing up liveCache data for SCM 4.0 or higher
Also, take a look of this thread:
http://scn.sap.com/message/7599491#7599491
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.