Hi All,

   Is their any stranded report to represent Planned (forecast) Date Vs Actual Date Variance in Graphical format . I check all std. for Graph format but no such std report shows date wise representation  .

Thanks ,

Virendra 

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello Dnyanesh,

After you run CN41 select Columns and then use graph, Ctrl+Shift+F7, Can you try this?

Deepak


former_member249141
Participant
0 Kudos

Hi Deepak,

I have already check  all Graphs  but no any  Graph shows representation against dates.

please suggest . It shows against %of processing , POC ... etc but not against dates

Thanks ,

Virendra 

former_member210872
Participant
0 Kudos

Hi Virendra,

You can refere report CN41N to get actual & forecast dates in one report.

You have choice to select diff graphical formats there.

Hope this may help you.

With regads,

Dnyanesh

former_member249141
Participant
0 Kudos

Hi Dnyanesh,

Thanks for reply

But their is not possible to see  such Graph like  plan VS actual Date Variance  in CN41N

Thanks ,

Virendra .

sammar81
Employee
Employee
0 Kudos

Hi Virendra,

The specific requirement cannot be met with standard reports.. you need to get it developed or maybe  try BO if its implemented in your place..

Regards

Sammar

sammar81
Employee
Employee
0 Kudos

Hi Virendra,

Nothing in standard SAP PS which i am aware of. Go for the development..