Dear All,

We could see an Amount of 10,000 as plan  in the Report  - S_ALR_87013543.

1) There are no PR's created,

2) No value is Maintained in CJR2.

3) The Value is not found in RPSCO.

We executed  CJEN & CJBN   .. but it is still showing in the report.

We could not locate the value. Kindly help.

Thanks in Advance.

Regards,

Shareeq

Accepted Solutions (1)

Accepted Solutions (1)

sammar81
Employee
Employee
0 Kudos

Hi Shareeq,

Any unit costing/network planning being done on the WBS where this cost is appearing? Please check that as well..

Else next option would be to raise an OSS message, doesn't seem to be the right program behaviour for the report..

Hope it  helps..

Sammar

Answers (3)

Answers (3)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please check in GRR3, report 6PP2-001, Project Plan Column and its charachteristic Values.

Specifically the Value Types mentioned.

Hope it helps!

Thanks and Regards,

Varshal Kachole

Former Member
0 Kudos

Hi,

Check Easy cost planning, or if you add any material, services in your structure.

Regards,

Chaitanya Parchure

former_member210872
Participant
0 Kudos

Hi,

Go CJ20n, Click on easy cost plan, Please check whether Easy Cost plan has maintained against that WBS.

With regards,

Dnyanesh

shareeq_hussain
Active Participant
0 Kudos

ECP not maintained.