on 09-25-2014 1:20 PM
Dear All,
I am facing issue while doing MB1A.
i am giving i/p as a plant,movement type 281.
Inside screen i am entering network no and activity no.
after that i am getting error.
Message no. KI293
The given network can only be assigned to directly. A network activity is not a permitted entry.
Overwrite the activity number entered.
Hello sappp Pranav
You should note the customizing changes in OPUV will only
works for newly created networks
Projects created before the changes, the value has already been updated in the DB table.
That is, field AFKO-NETZKONT was updated as "1" ( Header-assigned network)
when the project was created, based on the old customizing.
So you may have to undo the link and link it with a newly created project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pranav,
I am not getting you properly.
Let me try at once.
you are trying to consume material at activity level.
check that activity number exist with network or it might be deleted(DLFL)
I hope it will help.
Thanks & Regards
Rahul Bansal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pranav,
Could you please run transaction OPUV and check the network
type for the affected plant? Is flag ActvtyAcctAsgn (OBJNR_VORG)
set or not? If it is not set then, it means costs can only be carried
on header level for this network. Therefore this network must not be
used with an activity number when used as account assignment object.
So, if you want to use the activity number as a account assignment
object, please set flag OBJNR_VORG .
BR,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Looks like a header assigned Network.
Which SAP version are you operating on?
Here is the source for your issue: (Please implement the solution below)
Activity account assignment not allowed for this network
You cannot write any costs to the activity for the network whose key you have maintained.
The costs for the network can only be written to the network header.
Processing stopped.
1. Check that you have maintained the proper key for the network. Make any necessary changes.
2. Delete the key for the activity.
Hope it helps!
Thanks and Regards,
Varshal Kachole
Message was edited by: Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.