on 09-25-2014 6:17 AM
Dear gurus,
How to Restrict not to create PO when there is no sufficient budget for a project .Before EHP 6 up gradation system stops at the time of PO creation itself and through error message and now System is allowing to create PO even though there is no sufficient budget in Project and throwing error message at the time of PO releasing for excess amount .
For example:
Project Budget is Rs 1000
PR Price is Rs 1000
PO Price is Rs 1100
herein this case system allows to create PO and when going to release it throws error message ( Budget Exceeded for Rs 100). I want to restrict it at the time of PO creation itself
there is no tolerance for profile
Regards
Ambarish
Hi,
Please check if BAdi (ME_COMMTMNT_PO_REL_C) is active.
Hope it Helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
First of all, do not mix or confuse with budget release and error message at PO while exceeding the budget. Both are different process.
Now, request you to check your tolerance group setting in SPRO. I hope it is "++". (Go to SPRO->Project Systems->Costs->Budget->Define Tolerance Limit).
If it is already "++" over there, then execute CJEN followed by CJBN as suggested by Sammar.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ambarish,
Is the Availability Control active for the PO checks? If yes try running the CJEN and CJBN to reconstruct the AVAC. And try again, it is standard functionality should work..
Hope it helps..
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.