on 03-30-2007 9:58 PM
Hello Experts,
I have created two different Production Versions in ECC with different validity dates
and defined two different activities(like Run & Setup) in the Master Recipe. i ciffed these production versions to APO .The problem is,here these activities are not being displayed for the second PDS.
In ECC it looks like below:
0111 11.03.2007 to 11.05.2007 run produce
0112 12.05.2007 to 12.08.2007 run produce
IN APO it looks like below:
0111 11.03.2007 to 11.05.2007 run produce
0112 12.05.2007 to 12.08.2007 C
but if i overlap the validity dates then i am getting activities in both the PDS.
Hope this makes sense and clear. Can anyone please explain me why this is happening?
Thanks,
SP
You can change this system behavior by implementing the BAdI method
/SAPAPO/CURTO_SNP=>CIF_IMPORT. In this method you will find the
parameter CV_SNP_ROUTING_EXPL which defines the explosion date for the
PDS generation. This parameter can be adjusted to your needs in this
BAdI method e.g. by using the DATE_FROM form the production version.
KenSnyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have the same problem.. any production version with validity dates after another production version does NOT cif across correctly. I submitted an oss message but have not heard back yet.
Ken Snyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.