on 09-25-2014 6:26 AM
Hi gurus,
when i am trying to do cost & revenue planning in CJ40 & CJ42, i am not getting cost elements. but i have assign costing variant, primary cost element group and revenue element group. where i did mistake in planning profiles or any where in configuration.
so please suggest.....
Hi Siddu,
I remember, in CJR2 transaction you can do cost element planning, which in turn gets updated in CJ40.
Can you do check whether this works ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siddu,
Can you share the screen shot of your Planning profile? Also is the same planning profile being used in Projects where you are trying CJ40/CJ42?
Secondly can you check in extras whats the error message you are getting when trying to do Cost element planning..
Also try CJR2 and see if that works?
hope it helps
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.