Hi,
Check the planned cost in CJ40 or S_ALR_87013542 etc.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Maria Terence,
if I Plan cost in CJ40 it update in Budget CJ30 in Planned cost column. But If I assign Material and services that cost not Updated in cj30 Planned cost column
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jayendra,
Is that Planned Cost / Budget ?
Sorry i could not understand your query
Thanks
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jayendra,
The screen shots which you have attached are both of CJ30. Can you send the screen shots for Planned cost as well for this project? Are you using CJ40 for Planning or Network Costing or ECP? Are the planned values available in Planned Reports in PS? If it is ECP then the planned values will not be available in CJ30, if it is the other two then need to check..
Can you also check if the Planning Profile and Budget Profile are in sync? and what's the cost planning version you are using to plan cost?
Hope it helps..
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.