Hi Gurus,
In performing the integration of the billing plan between PS and SD, when using a milestone directly into a WBS Element, the system displays the "Sales doc. Date" option. But including it below a task with a network this option is not displayed.
Does anyone have any tips?
Thank you,
Márcio
Hi Marcio,
Sales Document date Tick is available to milestone attached to both WBS and Activity.
You may hide the sales doc date tick in field selection.
Go in T code OPUC (field selection of network details) - make Sales document date un hide.
With regards,
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Marcio,
Milestones are assigned to individual WBS elements or network activities. They are never assigned to Network directly .. Rather it is not possible to assign Milestone to Network...
Please clarify what do u mean by including it below a task with a network.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.