on 09-23-2014 10:52 AM
Hello,
I would have a question regarding that how is it possible to delete automatically the scheduling lines. On raw material level the MRP Type is VB (manual reorder point planning) and I would like to know that if the total scheduled quantity is over the reorder point then the system is able to delete automatically somehow those lines which are not necessary?
Any idea?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Péter Horváth ;
Can you try belowed steps ?
1- Find your schedule line category for raw material item.
2- Go to VOV6 & find your related schedule line category.
3- You will see ' Req./Assembly' , this tick related with 'Transfer of requirements'. If you untick this ,you stop transfering of requirements.
4- After check , VOV7 --> 'Schedule line allowed' and get information with F1.
But ; if you want to check this configuratios with a restriction like a ' I would like to know that if the total scheduled quantity is over the reorder point then the system is able to delete automatically somehow those lines ' focus on a ABAPER.
Regards.
M.Ozgur Unal