on 09-21-2014 4:53 AM
One of the low delivery priority customer place order for 100 quantity but his requested delivery date is 10-10-2014 and one more high delivery priority customer placed order for 50 quantity his requested delivery date 28-09-2014. as a consultant what will we do and ware is the control.
hi Rajendra
Do back order processing. so that you can change and delivery to the high priority customer first.
regards
Gopi