As a consultent what will we do...

Former Member
0 Kudos

One of the low delivery priority customer place order for 100 quantity but his requested delivery date is 10-10-2014 and one more high delivery priority customer placed order for 50 quantity his requested delivery date 28-09-2014. as a consultant what will we do and ware is the control.          

Accepted Solutions (0)

Answers (1)

Answers (1)

ajith_kumar10
Participant
0 Kudos

hi Rajendra

Do back order processing. so that you can change and delivery to the high priority customer first.

regards

Gopi