Production order not considering in-house production time from material master

Hello experts,

I am trying to create a Production order from CO01, and i have entered the Basic end date as 09/26/2014. and the start date was determined automatically as 09/26/2014. But, we have an in-house production time of 3 days in Material master. I would think Production order creation considers the in-house production time of 3 days and put the Basic start date as "  09/23/2014". But it didn't.

We don't want the scheduling to be done using routing,. We want it to consider inhouse production time from maetrail master only.

Please help.

Thanks,    

Swathi

Former Member
replied

Hello

The production order dates are always calculated from the routing explosion. The in-house production time is not considered for production order scheduling, only for planned orders.

You may try to use BAdI WORKORDER_UPDATE to change the production order dates according to your own logic.

Best regards

Caetano Almeida