Hello experts,
I am trying to create a Production order from CO01, and i have entered the Basic end date as 09/26/2014. and the start date was determined automatically as 09/26/2014. But, we have an in-house production time of 3 days in Material master. I would think Production order creation considers the in-house production time of 3 days and put the Basic start date as " 09/23/2014". But it didn't.
We don't want the scheduling to be done using routing,. We want it to consider inhouse production time from maetrail master only.
Please help.
Thanks,
Swathi
Hello
The production order dates are always calculated from the routing explosion. The in-house production time is not considered for production order scheduling, only for planned orders.
You may try to use BAdI WORKORDER_UPDATE to change the production order dates according to your own logic.
Best regards
Caetano Almeida
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Swathi,
time in material master is used for calculate a explosion date, with this last date the system will try to explode bom and routing.
If the material header has a routing this will have priority on master data internal production.
If you don't consider routing time you can run mrp whit value 1 in scheduling parameter so that will be use only time present in MRP1 View (Production internal time)
In alternative you can use as correctly said Caetano BAdI WORKORDER_UPDATE in order to change data and other date.
Daniele