Maintenance plan package change resulting in incorrect call dates

Former Member
0 Kudos

When we change a maintenance package on an existing maintenance plan to a package whose frequency is not an exact multiple of the previous package (for example, changing from a 6M 180-day package to a 1Y 365-day package) and then restart the plan, the call horizon of the plan seems to be ignored and the new call dates are always a day or so before the plan date regardles

Why is the call horizon being ignored in this situation?

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

David,

SAP do not recommend mixing UoMs within the same strategy (e.g. Months and Days) as this can cause scheduling inconsistencies.

You would be better off having two strategies, one based on Months, and one based on Days.

PeteA

Answers (1)

Answers (1)

rakesh_mane
Active Contributor
0 Kudos

Hello

Please check the Option Start in Cycle while scheduling the Plan.

Also refer the below thread too

http://scn.sap.com/thread/1788240

Br

Rakesh