tentative work and forecast work

0 Kudos

Hello everyone,

In CNS41, 2 fields are displayed for work : tentative work and forecast work.

what is the difference between the two, how are they calculated ?

Thank you for your help.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

hi Narender,

I found the following confirmations:

6310094/0010/0132

actual (total) = 8

Remaining (last confirmation) = 0

final confirmation = no

6310094/0010/0140

actual (total) = 68.25

Remaining (last confirmation) = 0

final confirmation = yes

6310094/0030/3541

no confirmation

Thanks.

Former Member
0 Kudos

JP,

Tentative work is the total estimate of the work that you have defined for each activity.However Forecast work: Actual work + remaining work. Can you provide us screenshots if you are finding any issues in the calculation of forecast work?

Regards

Varun

0 Kudos

Hi Varun,

in fact i would understand how is calculated  the remaining work.

sometimes tentative work and forecast work are differents, for example :

for network/activity/activ. element : 63100094/0010/0132
•work = 0
•actual = 8
•remaining = 0
•forecast = 0
•tentative = 8


for activity element 63100094/0010/0140 :
•work = 42
•actual = 68,25
•remaining = 0
•forecast = 68,25
•tentative = 68,25


for activity element 6310094/0030/3541
•work = 171
•actual = 0
•remaining = 171
•forecast = 0
•tentative = 171


Can you explain these cases ?


thanks in advance.

Former Member
0 Kudos

HI JP,

Can you also check the confirmation of these activities? Since these might also effect the calculation for forecast and tentative field.

Hope this helps.

Thanks and regards,

NKS.

0 Kudos

hi Narender,

I found the following confirmations:

6310094/0010/0132

actual (total) = 8

Remaining (last confirmation) = 0

final confirmation = no

6310094/0010/0140

actual (total) = 68.25

Remaining (last confirmation) = 0

final confirmation = yes

6310094/0030/3541

no confirmation

Thanks.