Hello everyone,
In CNS41, 2 fields are displayed for work : tentative work and forecast work.
what is the difference between the two, how are they calculated ?
Thank you for your help.
hi Narender,
I found the following confirmations:
6310094/0010/0132
actual (total) = 8
Remaining (last confirmation) = 0
final confirmation = no
6310094/0010/0140
actual (total) = 68.25
Remaining (last confirmation) = 0
final confirmation = yes
6310094/0030/3541
no confirmation
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
JP,
Tentative work is the total estimate of the work that you have defined for each activity.However Forecast work: Actual work + remaining work. Can you provide us screenshots if you are finding any issues in the calculation of forecast work?
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varun,
in fact i would understand how is calculated the remaining work.
sometimes tentative work and forecast work are differents, for example :
for network/activity/activ. element : 63100094/0010/0132
•work = 0
•actual = 8
•remaining = 0
•forecast = 0
•tentative = 8
for activity element 63100094/0010/0140 :
•work = 42
•actual = 68,25
•remaining = 0
•forecast = 68,25
•tentative = 68,25
for activity element 6310094/0030/3541
•work = 171
•actual = 0
•remaining = 171
•forecast = 0
•tentative = 171
Can you explain these cases ?
thanks in advance.