Release changeable indicator 6 not working


Hi MM experts,

n IPO Release strategy, it is configured like this.  Release indicator Y is blocked with changeable indicator 4 and Release indicator Z is Released with changeable indicator 6.

One PO is created, released, and outputted (print through ME9F).

Now user is changing the PO in the qty field; it is increased (10 EA to 15 EA). New release is not triggering. As per the changeable indicator 6; it should trigger new release strategy; Its not triggering.

pl help, Thanks in advance

Regards

Subbu

Former Member
replied

Check the SAP Note 1961482 - Reset release strategy when version number is set as Characteristic in Customizing.

It says that you can re-trigger release strategy when the version is complete.

Go to ME22N, in version tab, just click on the option "Complete Version"

Then click save and then check release strategy tab. Your release strategy will be reset.

1 View this answer in context