Preq release strategy tab disappears

We are having an issue where a few odd times, we will find that a Preq is missing its Release Strategy Tab. Here is an example, and my findings so far below the image.


Checking the Workflow, I see there was a workflow started, so I know the release strategy must have kicked in.

I see that the workflow went to error, with the error saying "No Authorization to Release"

However I checked the user, and they do have the correct Release Level Role.

So I'm not sure where to check next?

Tags:
replied

We finally found out what the issue was with this one. It was happening on Service Preqs where they had entered a value in the Supplying Plant field. If this is cleared and the preq saved, the release strategy comes back. Our new consultant found that we can make a config change to not allow a supplying plant to be entered on a Service Preq to prevent this from happening again in the future.