How to Schedule a Report to Run on a Specific Business Day and Not on the Weekend

Hi,

Is there a way to schedule a Webi report to run on a specific Business Day? For example, if I wanted a report to run on the 3rd day of every month, but when the 3rd day for a particular month landed on a Saturday or Sunday, then Monday would automatically be chosen instead. Is that possible?

Thanks,

Michael

Tags:
Former Member

Helpful Answer

by