Hello Experts,
I have configured Email alerts for info package which are connected with Universal data connect .
During data loading info package status turns to red and message shows "Error in source system"
where are step status shows "sucessfully completed" as below shown
So info package turn to red but Email alerts are not triggered due t ostatus shows completed.
Now how to overcome this situation to make sure email alerts will work in this situtation.
Thanks
Hi,
First check your data source is active or not in source system?
1)if not run the program RSDS_DATASOURCE_ACTIVATE_ALL- provide your datasource name do not run for all
check the check box for "Only Inactive objects".
2)replicate your datasource in rsa1 and execute infopackage
hope it will resolve your problem.
Regards,
Ganesh Bothe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check your info pack failure error.
Again replicate your data source into bw and activate it.
Later you can trigger your chain and see.
What conditions you used to send alerts?
if info pack was succeeded then send alert?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.