on 09-17-2014 5:25 PM
Hi Gurus ,
I have created one new production order by copying existing one in Dev system. I am able to save the production order but system has also copied number range of old production order . when it was transported to Quality system then by default number range also been copied to quality system for new production order although I wanted to assign the same number range which has been copied .
Please let us know whether this procedure is correct or not. Or will it overwrite the production order number range in “PRD” when it will move the same .
Thanks,
Regards ,
Aman
Aman,
When you create a order with copying existing order then new order number should be different from old order.
I hope you are aware that order number ranges can be maintained in CO82.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran ,
Yes , I am aware for co82 how to maintain the number range . As per client requirement they want the same number range for the new production order type also & they don't want to user the old production order type . Actually as per requirement new order type should have same setting like old order type .
Number range mentioned for both order type(old & new ) is as below .
In dev system .
100000000 – 199999999 1000000020
In Quality system .
100000000 – 199999999 1000038750
When all the setting was transported to quality system then it was not overwrite the existing running number .
I means it has started giving number from 1000038751 ……
Please let me know whether it is right practice ? or should I delete the new order type in “Dev” System & create recreate the same without taking any reference . Then transport the same again in Quality then maintain the number range through C082 in quality
Thanks ,
Regards ,
Aman
Hi Kiran ,
Yes , I am aware for co82 how to maintain the number range . As per client requirement they want the same number range for the new production order type also . Actually as per requirement new order type should have same setting like old order type .
Number range mentioned for both order type(old & new ) is as below .
In dev system .
100000000 – 199999999 1000000020
In Quality system .
100000000 – 199999999 1000038750
When all the setting was transported to quality system then it was not overwrite the existing running number .
I means it has started giving number from 1000038751 ……
Please let me know whether it is right practice ? or should I delete the new order type in “Dev” System & create recreate the same without taking any reference . Then transport the same again in Quality then maintain the number range through C082 in quality
Thanks ,
Regards ,
Aman
Hi Kiran /Mariano ,
In my case number range interval group was already maintained in both the server & I didn’t have to create it separately & client wants to have same number range for new order type . When I copied the old order type through “OPJH” to create new order type & done all the other seting .. Then after I saw in CO82 it has already taken the same number group like old production order type have in “Dev” . I didn’t assign it manually anywhere .
In Dev system number range is maintained as below for new order type
100000000 – 199999999 1000000020
When this setting was transported to “Quality” then new order type was automatically assigned to same number group .
In Quality system number range is maintained as below for new order type
100000000 – 199999999 1000038750
When setting was transported to Quality it has not overwrite the current number & started giving number like 1000038751..etc .
My question is if we transport the order type setting in “PRD” so will it create inconsistency or not .
In Quality I don’t see any problem .
Thanks ,
Regards ,
Aman
Hi,
Have you check the note mentioned in my first post?
This note explain how this issue can be fixed.
1536355 - Number range assignment after you transport order
types
Kind Regards,
Mariano
Aman,
Please note if you are not doing any changes in Number Ranges then obviously it would not overwrite the number ranges in Target system when you transport them.
Now in your case you have done configuration for new order type with copying old order type so there is no changes in Number range group so when you transport them to production it would not disturb or overwrite your current number range in production system.
You already had experienced same with transporting to QAS same way it works with PRD.
BR
KK
Hi,
You will need to overwrite the number ranges using t-code: CO82
Check this note to fix this issue:
Note 1536355 - Number range assignment after you transport order types
Symptom
In Customizing of production order types (transaction OPJH), you make changes and then transport them. This transport overwrites the number range assignment in the target system. As a result, incorrect number ranges are used for this production order type.
Other terms
Order type, number range assignment, NUMKR, Customizing, T003O
OPJH, maintain production order types, V_T003O_PP
CORN, order type, process order, V_T003O-40
Reason and Prerequisites
The system design contains errors.
Look at the inside the note to see the solution...
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.