Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

List of Values are not getting scheduled in Business View Manager...

I have created a Business View which has 15 business elements and since all 15 reports use singlt LoV so created only one Lov.. So far it is fine... but when I schedule the List of Values and check the status after the schedule... there was no update on the schedule status (Either Pass or Fail) was not displayed and there is always only one message.

There is no scheduled List of Values instance. This list of values executes on demand.

I was unable to understand the root cause on what would be the possible reason for this behaviour.

Can experts please help me to overcome this.

Thanks for your time

Siva

Tags:
Not what you were looking for? View more on this topic or Ask a question