Hello,

we have a problem concerning the transfer of the master data procurement indicator and material prices.

If we want to determine the transfer, we get the following message:

"

Could not determine any plant data in SAP GTS

Message no. /SAPSLL/PLUGINR3143"

Does anybody know why we cannot transfer the data?

Thanks for any help.

Best Regards,

Jörg

Accepted Solutions (1)

Accepted Solutions (1)

thomasrausch
Active Participant

Hallo,

Use Customizin you found under general setting-->organizational structure. Here you can

define Plant-Based BOM Evaluation or cross-plant evaluation.

Regards

Thomas

Former Member
0 Kudos

Hello Thomas,

can you explain more detailed where i can find the TC in Spro?

Thanks for help

Regards,

Jörg

thomasrausch
Active Participant
0 Kudos

Hello Jörg,

see the picture. The last two pathes

 


Regards

Thomas

Former Member
0 Kudos

Hello Thomas,

thanks for the help. My english is not that good and so now with the screenprint I find the TC.

Problem is solved with editing the factory to the right logical system.

Thanks,

Jörg

Answers (1)

Answers (1)

former_member215181
Active Contributor

Hi Jörg,


The transfer depends on obtaining the GTS configuration during the ERP processing.  There is an Remote Function Call made to GTS for that purpose.  So, there seem to be 3 possibilities:


  1. The destination of the GTS system cannot be determined > check your set-up (are other transfers working ok?).
  2. The RFC call is failing > check the permissions of the relevant user.
  3. The GTS configuration is incomplete or wrong > check that there is an entry in either table /SAPSLL/MODWRK or /SAPSLL/MODWG for the ERP Logical System.

Hope that helps.

Regards,

Dave

Former Member
0 Kudos

Hi Dave,

In the GTS table /SAPSLL/MODWRK i see the reference from factory to logical Feeder System, but not the correct Logical Feeder System. Can you tell me where I can edit the correct logical ERP System and refer to the factory in ERP.

Do you think this is the problem?

Thanks for help,

Regards,

Jörg

former_member215181
Active Contributor
0 Kudos

Hi Jörg,

Yes, that is probably the problem.  You make the entries in configuration (as also mentioned by Thomas below).  If the existing entry has the wrong Logical System, just copy it with the correct value, and then delete the existing entry.

Regards,

Dave

Former Member
0 Kudos

Hello Dave,

thanks for the help. The problem is solved with Yours and Thomas help.

Regards,

Jörg