Material scrap factor without increasing BOM qty.

Hello SAP experts

In our factory wrong material is mostly scraped once in a week. Unfortunately this situation few times generates parts shortage on production due to material which we can't be used and which is not removed from SAP.

I want to avoid manual material forecasting in MD62 and Safety stock increasing.

is there possibility to increase material demand by scrap factor (or similar setting) without increasing bom qty (i can't increase it due to cycle counts and stock accuracy verification)