Problem Changing MRP Type Per MRP Area

Hello PP gurus,

I'm trying to implement "Planning Time Fence" to be able to automatically "firm" planned orders falling within the time fence. I have gone into Material Master Record and used MRP Type P1 under MRP View 1 (see image below) to be able to use firming. However, when I use MD04 to look at Stock Requirements List for this item, I get/see the MRP type "PD" (see second image below). I assume that there is a link/table that connects MRP Type with either the MRP Area or at Plant Level and that link/table overrides what I entered in Material Master Record.

My question is: How do I maintain the MRP Type at the MRP Area or Plant level? What's the path or Transaction Code I should use? If I can maintain this setting, my problem would be solved. I will gladly reward points for helpful/correct answers.

Tags:
Former Member
replied

Hello Bello,

You want update the MRP type in MRP area,

follow below step

1. Go to  MRP view1

2. Select MRP Area

3. Material data filed in MRP area level

   Update the MRP Type in filed, and Save

After changes Run MRP again

Please follow above step and confirm the changes