on 09-16-2014 11:47 AM
Hi PS/CO Experts,
Can you please suggest a method in which we can move the costs that have already been posted on a cost object in the previous fiscal year (Please note that the previous fiscal year has been closed) to the current fiscal year?
Regards
Varun
Hi All,
Adding to this discussion, the business is not willing to open any periods of previous fiscal year. If we carry out full settlement will we be in a position to use the same WBSe again for posting actuals and then settling them accordingly?
What would be the procedure to carry out full settlement to ensure that there are no left over amounts in previous fiscal year?
Any help shall be much appreciated.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
To summarize this , the final solution to this problem would be to manually repost the costs using kb11n from WBSe to the cost center in the previous period and then repost this amount from the cost center to the same WBSe in the current period and settle the amount accordingly. (As per OSS Note 140672 suggested by Varshal). Please correct me if my understanding is wrong.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To repost the values in previous month which is in last FY you need to open the FI periods which you said is not possible in your scenario!!
Because if you can open the closed period you dont need to do all this.. just reverse the transaction and post a new one.. Best practice would be that only.. I am not sure why there is so much fuss @ Opening of a period??
Also why FI guys are not taking it up in their stride?? Why from PS you have to get it sorted?? Just curious..
if Opening Up of period is allowed. Go with the standard Route would be my suggestion..
Cheers
Sammar
Hi
Cost posting will be possible using KB11n/KB61 etc. Not sure whether reversal will work or not as previous periods are already closed.So technically, reversal should not happen.
Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varshal,
That was exactly what I was having in mind to use KB11N/KB15N to transfer the costs from the WBS element posted in the previous fiscal year to the current fiscal year. However will it be ok if I suggest creation of new WBS elements to move out the costs posted in the previous fiscal year to the current fiscal year and then resettle these values in the current period? I dont think this provides an answer. The problem here is that the business is not willing to open the previously closed financial periods.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Not necesarily new Cost object has to be A WBSe. It can be a Cost center as well, as long as a Cost Obejct remains as a cost Object.
Moreover, we do not need to open any previous peiods/ years for the Settlement. (You may refer http://service.sap.com/sap/support/notes/424139 in addition to the earlier Note).
Other than the option suggested earlier, there is no other option but to open period which is not advised.
Thanks and Regards,
Varshal Kachole
Hi Sammar,
It was a journal entry from FI. The business is not willing to re-open the closed financial periods.However the controlling periods are open.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varshal,
The OSS note you have suggested is something to do with production/process orders.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sammar/Varshal,
Thanks a lot for your prompt replies. The exact business requirement is to move the actuals posted on a WBSe from previous fiscal year to current fiscal year. Please note that the controlling periods are open but the financial periods have been closed. Is there a way in controlling to move the actuals posted on a WBSe from previous fiscal year to current fiscal year (Current Period)? Please note that the costs posted on the WBSe have not been reversed/settled.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please Settle the Cost from Previous year from WBS to a new Cost Object (e.g. another WBS) in the current Period/Year. Refer to the The Note suggested for the Options.
Then Use the KB11N/KB15N from the New Cost Object to the Old WBS ELements.
Hope It helps!!
Thanks and Regards,
Varshal Kachole
Hi,
Please review http://service.sap.com/sap/support/notes/140672
Hope it helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varun,
You need to post a reversal document for the same amount and again do the posting in this financial year?
Is the cost which you want to reverse already settled from the Project to its receiver? What's the reason of this reversal?
Can you elaborate on your need a bit more?
Cheers
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.