Message no. CJ057
i have created a Project and Budgeted the same.
now i want to delete the same Project.
i have removed the budget and made it to zero. availability control is not updated.
no orders made against the project.
how do i delete the project?
pls help.
Hi Suhas,
First of all why you want to delete the project at all?
Secondly if you have released the project you can not delete the same.
I would suggest you to close the project with system status CLSD and then put a deletion flag with system status DLFL on the project.
Hope this will fulfill your requirement and answers your query.
Regards,
Somya De
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Execute Transaction OPSX to reset the BUDG status and delete the Project.
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suhas,
Why you want to delete the Project? You can very well close it off? As you said no cost is posted to the Project.. It will also serve your purpose..
Otherwise the dirty way of doing it would be to Delete the Budgeted Status from JEST table for these project object. If you have debug access you can do it your self.. But I am not sure if it will have any other impact.. It shouldn't as you don't have any cost associated with it..
My first preference would be to try the first option of Closing the Project..
Cheers
Sammar
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.