CM21 - Capacity planning table

Hello,

I have some general questions regarding planning table:

  • After partial production order confirmation the remaining production time is shorter as before - how to refresh planing table to see the progress?

    1. Is it needed to use deallocate/dispatch function?
    2. Or there are other functions available?

        

          If we use deallocate/dispatch functions the basic dates will  be changed, and we want to avoid it.

  • How to stop planing table from changing basic dates? Or its not possible?

  • Is it possible to plan two production orders at the same work center at the same time (parallel production)? We are able to run two orders on the same machine.

Thanks in advance,

Evgenij