We have a requirement from management for Having budget control based on department wise.
For that we are trying out substitution rule by which Pm order is replaced with Internal order .we are having a budget profile and budget for internal order.Now we are able to control budget and system stopping if budget exceeded in migo transaction .We are replacing pm order with IO order with substitution with pm order number range. Issue is after having this setting actual cost is not updating in Pm order and pm report.
Same is getting updated in mseg against pm order.
With regards
Anand.M
Hi Anand
Please add the budget profile at Plant maintenance order level no need to add any substitution rule
budget should also be control at order level
Thanks
trinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Issue is you do not have any posting on PM order now. the costs are directly moving to IO because of substitution.
Why the budgeting for PM Order is not tried and tested?
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.