MRP Planning

Former Member
0 Kudos


Hello Experts,

I want to configure business senario for demand Planning, Please help

PIR created Month wise (M1, M2, M3) after MRP run planned order is required for M1 on fortnightly basis (1 Planned order for first 15 Days and 1 Planned order for last 15 days)

I have created new Lot Size "Z1" with below mentioned values & Planning calender period is of 15 days period.

Lot-sizing procedure "P" (Period lot-sizing procedure)

No. of periods  2

Lot-size indicator   W (Period lot size: weekly lot/dyn. lot-siz)

Please suggest how to configure the same. Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please observe that, setting a periodic lot sizing procedure will not split your PIR. That means, if the PIR was created on the beginning of the month, it will fall into the first period and a replenishment proposal will be created to cover the entire PIR on this period.

I suggest you to split your PIR before running MRP.

Otherwise, try to define a takt time and a maximum or fixed lot sizing procedure.

BR

Caetano

Former Member
0 Kudos

Is there any configuration to create 2 production orders after getting single planned order of M1, Please suggest

kiran_kumar179
Active Contributor
0 Kudos

Mayur,

In CO40 you have option to convert planned order to production order partially.

BR

KK