maulik_vania
Explorer
0 Kudos

Dear All,

I have certain material(20 Material) which use reorder base planning.

For this 20 material I want to run MRP in background for every 20 min.

What master and special customizing I need to define for such scenario?

Regards,

Maulik

Accepted Solutions (1)

Accepted Solutions (1)

maulik_vania
Explorer
0 Kudos

Hello Mariano,

thank ink you for the reply.

Is it possible to use MRP group instead of MRP controller?

Regards,

Maulik

kiran_kumar179
Active Contributor
0 Kudos

MMV,

Yes you can run MRP based on MRP group also with same user exit.


Refer below thread http://scn.sap.com/message/4806525#4806525

BR
KK

marianoc
Active Contributor
0 Kudos

Hi Mailik,

I have never tried, but it seems it is possible. Look at this thread:

Kind Regards,

Mariano

Answers (3)

Answers (3)

maulik_vania
Explorer
0 Kudos

thank you for the answer.

marianoc
Active Contributor
0 Kudos

Hi,

You can run the MRP by MRP controller. The MRP controller will need to be assigned to your 20 materials.

Then you can schedule an MRP run every 20 min in transaction MDBT. When you save the variant, you can filter by MRP controller. To be able to do it, you will need to enhanced the MRP run using the

prefefined SAP 'user exit' M61X0001.

Other option would be to run an MPS for these materials (MD40). You will need to assgn MRP Type M1 to M4 to your 20 materials.

Kind Regards,

Mariano

kiran_kumar179
Active Contributor
0 Kudos

MMV,

If you want to run MRP for only these 20 materials then you need to use a user exit with which you can restrict MRP to only few selected materials.

Refer Below link for steps http://scn.sap.com/docs/DOC-52852

Then you can create Variant and Schedule the job in background per your requirement.

BR
KK