CJ9E/CJ9G reset error

Former Member
0 Kudos

Hi,

I run CJ9E and CK9G for bulk (reverse/reset) and it says nothing to settle. When I check CJI4, the values are still there, the reversal did not
work.

However, I was able to reset for certain cost centers and not for others.

What could be the cause and how do I solve this so that I can reset?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Una,

Please refer to following SAP note if can help you.

301257 - KD250 with planned settlement/reset


Regards

Tushar

Former Member
0 Kudos

Hi,

The note refers to execution errors. When I run the settlement, it's blank, and then I reset, there's also nothing there and there's no error messages coming up. It is just blank. Settlement reversed is blank(zero) but when I check CJI4, the amount is still there.

Another thing is that this only happens for version 2. When I execute other versions (0 and 1) it works fine. I can settle and reverse.

Please assist.

regards

Answers (1)

Answers (1)

Former Member
0 Kudos

HI Una,

Follow the OSS notes:

799044 - Planned settlement rule: incorrect use data

1498252 - Advance development: Planned settlement after planned costs deleted

Thanks and regards,

Narender.