Operation scheduling during capacity leveling on work center

Dear Experts,

      Need help regarding the capacity leveling at work center. The scenario is as below

Order Nowork centerOperationWork
1001ABC001011 hrs
1001ABC00207 hrs
1002ABC001010 hrs
1002ABC00208 hrs


Two order , having two operations each , with same work center. The day's max capacity is 8 hr.

Now while I'm dispatching these orders for leveling , in CM25, I want system to schedule the completion of all operation related to Order 1001 first. Means first it should complete both operations (0010 & 0020) of order 1001 and then it should look for the available capacity and schedule order 1002 (Operation 0010 & 0020)

But in actual, system is scheduling operation 0010 of all the orders and then operation 0020 for all orders , means system schedule order 1001 (Op=0010), then it schedule 1002 (Op=0010)

Once all 0010 got scheduled, then system starts with 1001(Op=0020) followed by 1002 (Op=20)

Can you please advise , what settings need to be maintained in order to get the desired outcome.

Regards

Denny