Dispatching sequence: Structure KBED is not currently supported

Dear PP experts,

I have a question about collective conversion of planned orders (t-cd:CO41).

I got the error "Dispatching sequence: Structure KBED is not currently supported"  when I convert from planned order to production order with t-cd:CO41.

Do you have any solution about this issue ?

In t-cd:OPJK, I use the parameter below.

Former Member
replied

Hello

Please check the dispatching sequence key SAPSFCVER according to the below procedure, which is described on note 334455 - Message CY831 for availability check:

If you use a self-defined dispatching sequence key for the strategy for finite scheduling, you have to make sure that this key neither uses fields from structure KBED nor that this structure is assigned to the key.

For the correction of dispatching sequence key SAPSFCVER, you go ahead as follows:

Call Transaction CY39.

Go to the field selection for key SAPSFCVER.

Make make sure that "Order operation" (AFVG) is being used for the structures and that fields AFVGD-SSAVD and AFVGD-SSAVZ are used in the field selection in exactly this sequence.

Delete "Capacity requirement" (KBED) for the structures.

Save your changes.

BR

Caetano

0 View this answer in context