Hi,

We have a requirement that there are three operations 0010 , 0020 and 0030 .

The operation 0030 is a milestone confirmation , and the operation 0010 and 0020 are marked as confirmation possible but not neccessary.

But we don't want the user to select and enter confirmation for operations 0010 and 0020 by mistake.

In F4 selection it wont available , but still we can enter confirmations for 0010 and 0020 . Is there is any way to prevent this?

Accepted Solutions (0)

Answers (1)

Answers (1)

kiran_kumar179
Active Contributor
0 Kudos

Crazy,

Check below thread for same requirement http://scn.sap.com/thread/3394097

Br

KK

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

As I suggested on the previous thread , this functionality is not available on the standard system, however, you can implement this check with BAdI WORKORDER_CONFIRM.

BR
Caetano