Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Sufficient stock but MRP create planned order and purchase requisition .

Hi Expert,

After MRP run planned order and purchase requisition created . but the problem is for child material sufficient is there but still PR and plnd order is created .

MRP type PD, LOT size EX,Strategy group 10, for testing purpose I made safety stock 0, min lot size 0 , max lot size 0.

I cant find the cause why MRP create PR and Pland order for the material which has sufficient stock. Please help.

Former Member
Not what you were looking for? View more on this topic or Ask a question