Transport of BPS planning area (variables) without transp. all pl. levels

Former Member
0 Kudos

Hi!

Can anybody advice me, how to transport new variables which I have created to a planning area, without transporting all planning levels which belong to it?

I transported a few planning levels that include the new variables I created to the planning area. As a result, the planning levels are transported but the new variables are missing. I don´t want to transport the whole planning area, since it contains a development which is not ready yet. Can I transport the missing variables with SE15 (how?) or is there some other way to do it?

Grateful for any help,

Sari

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Sari,

Please execute program UPC_TRANSPORT_BPS_ALL and transport your variables without transporting any level or area.

Hope this helps.

Cheers

Srini

Former Member
0 Kudos

Thank you Srini!

This was just what I needed!

Thank you for your help!

Sari