Progress Analysis - Planned POC not being updated in CNE5

Dear SAP PS Experts

I have completed all the progress analysis configuration , and CNE5 report is showing the aggregated planned POC values (using time proportionality measurement method.) for the first period chosen in CNE1.


However, I re run the CNE1 say for new period it dosent updated the aggr.planned POCs in CNE5 Report.


I have also tried CJEN to reconstruct the PS info Database but the result is same , no update in planned POC's.


My questions are below :


1. Is there any thing which i am missing inorder to update the planned POCs based on period

2. when we tried doing this for a selected date ( say todays date for progress analysis) it gave wrong results , it acutally considering next period. i.e.- fixed date basis poc it also failed with incorrect values.



kindly please suggest the solution


regds

Avinash