Hi Brent,
Having seen the loop, I feel that the first line item is being referenced in PO.
Please try this -
Add a new line item to PR of extra quantity (without deleting the existing line item of 100,000 Qty).
Add a new line item at service level in PO with reference to the newly created PR line item for extra quantity.
Regards,
Akash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You are procuring Service with Service PR and Service PO with item category D where you have
activated AU as Unit of Measure at Item Level in t.code: ML91(in the field of Unit of Measure in item level field).
In you case you created PR with quantity 1AU with price 100,000 and then converted that PR to PO. Again,you just increase price for that PR to 200,000 with same quantity 1AU (without changing quantity which is not possible) for which you want to create/update the PO!
As you already created PR and PO for quantity 1AU with price 100,000.Now better add a another line item for same service PR in item overview segment with quantity 1AU with price 100,000 and then convert that new quantity 1AU with price 100,000 from PR to a another PO.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gibi,
Please check configuration settings for the system messages..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brent,
Please check any user exit or BADi written for the Quantity check in PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Target quantity is a field from a purchasing contract so there must be a contract referenced in the purchase requisition.
Check the contract and compare the target quantity with the total quantity of release orders. If appropriate you could increase the target quantity to allow creation of this order.
Regards
Robyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Brent
I've had a better look at the message now and it seems to be a services related message. Sorry for pointing you in the wrong direction.
Have you tried adding a second services item instead of increasing the quantity on the existing one? I have no idea if this is correct but there might be an unseen link between item 10 in the purchase order and the deleted item 10 in the requisition.
Regards
Robyn
Looking through the history of this, it’s a mess. But I think I see why this is happening now. The PR line 20 had a service line 10 for 100K which the PO was created on. The PR was edited to delete Service line 10 for 100K and create service line 20 for 200K. So the PO just lists PR line 20 as its source but not which Service Line. I think it is still trying to compare it to the service line 10 instead of the service line 20, maybe there is a link in the background that you can’t see on screen? I would think they would have to create a new line on the PO instead of changing it now. But I also see they have entered Invoices on this PO line above the 100K now, so I’m not sure if those have to be removed and re-entered under the new line or what?
History below.
PR 10000137 line 10
Created 5/13
Created as 100,000 EA, but no D indicator
Released 5/15
Deleted 5/21 11:43
PR 10000137 line 20
Created 5/21 (SS10 for 100K) (No release needed since same value since line 10 deleted?)
Edited 6/6 100K>200K (Release removed?)
SS 20 Created for 100K.
Marked Deleted 6/6
Released? 6/27
Undeleted 8/27
SS10 Deleted 8/27
SS20 Changed to 200
Released 9/4
PO 4500010764
Created 5/21 (Based on PR SS line 10)
Released 6/3
UOM changed 7/9 AU>CAD
Quantity Changed 1 AU > 100,000 AU
Try with adding new line item in existing PO. Is the error coming ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check whether any other PO exists for the PR - You may check the same in the status tab in the PR.
If not, you may add a new item at service level for the total PR quantity and check. You may use the service selection button at services level to copy from PR. Please check and revert back.
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I checked and no other POs exist for the PR. They would really not like to add a new line, but rather amend the existing line because they already have invoices against this line for the additional amount above the 100,000 that they need to now enter the SES/GR for. (We have it set to allow invoices before SES).