planning strategy 11 not creating planned orders

Hi all,

I am using planning strategy 11 to create planned order for gross requirements as shown in screen shot. But MD02 is not creating planned orders.

Plz help if i am missing some settings in config or masterdata. I have maintained strategy 11 ,production scheduling profile,MRP controller etc in master data.

cv.png (155517 B)
Former Member
replied

Hello Amit


Set the Mixed MRP indicator to 2 on the MRP view 3


Please check and confirm the changes,


Regards

Umesh Mali