Hi all,
I am using planning strategy 11 to create planned order for gross requirements as shown in screen shot. But MD02 is not creating planned orders.
Plz help if i am missing some settings in config or masterdata. I have maintained strategy 11 ,production scheduling profile,MRP controller etc in master data.
Hello Amit
Set the Mixed MRP indicator to 2 on the MRP view 3
Please check and confirm the changes,
Regards
Umesh Mali