Hi,

In my planning model  i have added a new keyfigure (say C) which on fulfilling a few conditions adds up two key figures say A and B.The logic for C = A+B  is written in a method which gets triggered through a planning sequence button in the planning workbook. But when users open the planning workbook they see all zeros for this new key figure though both A and B have values.Then if they enter any values for A or/and B then the value for C becames visible.

So is there anything that i can do to calculate C for all history data available in the cube.

Thanks for the help in advance.

Regards,

Rajeev Mishra

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Thanks.Got it.