on 09-11-2014 9:07 AM
Hi,i want to move sld of a PI 7.0 running production system from central solman 7.0 sld and set up a dedicated local sld for PI production system.
The steps i will follow are the following .Please correct me if i miss anything or if any steps are wrong.
1.Change in rz70 and visual administrator for sld host in production PI system and replicate
2.Export business system from existing solman sld (Home->Business System -> select production PI system)
3.Import this exported file in production PI sld ( Adminstation -> Content ->Import)
4.Change sldapicust entries and check sldcheck in production PI
5.Change entries in production PI exchange profile
6.Clear SLD cache
PI SLD experts,kindly help. thanks.
Hi
You also need to cleanup your local PI SLD, just in case it was used at some point in the past. Importing SLD will add/overwrite information, but will not delete the old information if the source doesn't have them. If you don't, you may end up with unnecessary and possibly conflicting components in your PI domain. Here is a blog on on SLD migration in case you need a quick reference: Migrating SLD Server on SAP XI | SAP NW Newbie
regards
AKD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anil,
Thank you.I saw the blog .Here again there is confusion about step 1 in the blog whcih tells to do a full export on the source even though the other 2 systems are not required.Why it is so ?
As mentioned in earlier post,exporting only the required Business system instead of FULL export has any issues ?
Hi
You will need the other two systems to be included in SLD. That would be for the transport of PI configuration objects to work properly. Check this link to understand this concept:
PI registers data in SLD that goes beyond the scope of Business System information. Apart from Business System information, Products and SWCs are used during design time. The runtime uses sub-system level data of SLD. See SAP Note 764176 to get a hint of how complex that data is.
Importing the FULL export is an easy way out, instead of correcting all that.
regards
AKD
Expanded the answer.
Hi Anil,
Thank you very much.My worry is that we have a lot of systems ( about 30 ) included in the existing solman SLD which are not only PI systems but ECC,BI,Portal,GRC systems also.So what to do with non PI systems which are imported in dedicated local production PI SLD from the FULL export ? Can I remove non PI systems which appear in Technical system,Business system,Content Maintenance list in production PI SLD ?
Hi,
I have exported successfully from source system (Solman).Then configured a local SLD on target xi system.Also made the levels of SAP_CR and model version in target system the same as that of the source by importing SAP_CR (in many steps ) and cim.SAP_CR is at 9.9 and model versio at 1.6.36.After this I tried to import the exported file in target xi system but it fails during the initial checks and gives the below message.
"The selected ALL 1.0 full import belongs to the export line ALL which is not compatible with the export line(s) SAP_CR of previous imports. The data of the selected import may possibly interfere with the previously imported data."
The equal level condition of SAP_CR mentioned in the note 1540435 ("Initially the target SLD should contain the same version of SAP CR content that is delivered with the initial full export " ) is fully satisfied.Then what went wrong in my case ? i have to do import of LD+NR export (in two steps seperately) and leave import of ALL export file ? Kindly reply.
Hi,
You need to do settings in SLD datasupplier also, which you have missed in your points.
Thanks and Regards,
Naveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You should follow this approach:
1. Move all SLD content from the old to the new SLD by a full-sync
2. Change all RZ70 and SLDAPICUST settings of all systems connected to the old SLD to the new SLD
3. Change the SLD client and SLD data supplier connection on PI to the new SLD
4. Deativate the old SLD or create a snyc from the new SLD to the old SLD to keep this updated if required.
Best Regards
Harald
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Thank you for your reply.Please find my queries.
1.I understand that in step 1 in your reply you mean to export all SLD content and then import in the
PI local SLD ( Export using Administration -> Content -> Export -> Export line -> ALL and Import
using Administration -> Content -> Import ).There is one thing to be noted here .I do not want to
move all systems from the exisiting SLD to the local SLD of the production PI.Only production PI
will be moved to its local SLD.In this case why I need to perform step 1 in you reply as this will
fetch the details of all other systems ?
I will be exporting/importing only Business system and landscape system will be populated
through rz70.After this I will also be checking the entries for production PI system under
Administration -> Content maintenance -> SAP_XI* classes.I hope this will appear automatically.
2.There is no SLD data supplier added in the existing SLD.So nothing will be done.
Kindly give your inputs on the above.Thank you.
1. Correct. If you only want to move a subset of objects, then you need to do this manually not via sync.
As soon as you have changed all data supplier settings of connected systems to the new SLD the technical systems should be updates accordingly.
2. Ok, then just deactivate or leave the old SLD as it is.
Best Regards
Harald
User | Count |
---|---|
76 | |
9 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.